A Literature Review from Project Management Point of View on Construction Phase Delays: Study on Oil and Gas EPC Projects in Indonesia

Authors

  • Rifky Basalim Universitas Nasional Jakarta
  • Tri Waluyo Universitas Nasional Jakarta
  • Suryono Efendi Universitas Nasional Jakarta

DOI:

https://doi.org/10.70062/globalmanagement.v3i1.508

Keywords:

Delay Factors, EPC, Indonesia, Project, Project Management

Abstract

Indonesia’s Oil and gas project construction continue face challenges notably delays that lead to underperformance. This study tries to describe the factors that causing delays in EPC oil and gas project in Indonesia from project management view. Started by overall study on cause of delays in construction worldwide, thus phenomenon on neighboring country (Malaysia) where Indonesian workers involved, then study continues with factors in Indonesia as overall, and include specific project which are South Sumatera and Sumbawa. Three main factors are always present in the cause of delays in EPC Project in Indonesia namely; contractor’s financial problem in funding the project, poor project planning and estimation leads to unrealistic determination of the duration, and ineffective change management by owner in project showed in resolving contract dispute, requirement changes, and dispute in understanding in contract articles. These factors are clearly present in EPC projects in Indonesia as main contributor in project delays together with two additional factors namely legal awareness and social community problems.

References

Al-Kharashi, A., & Skitmore, M. (2009). Causes of delays in Saudi Arabian public sector construction projects. Construction Management and Economics, 27(1), 3–23. https://doi.org/10.1080/01446190802541457

Gunawan, M. I., Suryana, H., Patra, O., & Nugraha, E. (2025). Analysis of delay factors in EPC power plant projects (Case study: PLTMG project in Sumbawa). JRSSEM, 4(11).

Gunduz, M., & Al-Naimi, N. H. (2022). Construction projects delay mitigation using integrated balanced scorecard and quality function deployment. Engineering, Construction and Architectural Management, 29(5), 2073–2105. https://doi.org/10.1108/ECAM-12-2020-1082

Ibrahim Khalid, F. J. (2017). The impact of poor planning and management on the duration of construction projects: A review. Multi-Knowledge Electronic Comprehensive Journal for Education and Science Publications (MECSJ), (2).

Iskandar, Hardjomuljadi, S., & Sulitio, H. (2021). The most influencing factors on the causes of construction claims and disputes in the EPC contract model of infrastructure projects in Indonesia. Review of International Geographical Education, 11(2), 80–91. https://doi.org/10.48047/rigeo.11.02.07

Kaming, P. F., Koesmargono, A., & Aji, B. W. (2019). Delay model for engineering procurement construction (EPC): A case of liquefied natural gas (LNG) projects in Indonesia. MATEC Web of Conferences, 270, 05010. https://doi.org/10.1051/matecconf/201927005010

Kassem, M. A., Khoiry, M. A., & Hamzah, N. (2021). Theoretical review on critical risk factors in oil and gas construction projects in Yemen. Engineering, Construction and Architectural Management, 28(4), 934–968. https://doi.org/10.1108/ECAM-03-2019-0123

Khalid, F. J. I. (2017). The impact of poor planning and management on the duration of construction projects: A review. MECSJ, (2).

Kumar Suppramaniam, S. U., Ismail, S., & Suppramaniam, S. (2018). Causes of delay in the construction phase of oil and gas projects in Malaysia. International Journal of Engineering & Technology, 7(2.29), 203–209. https://doi.org/10.14419/ijet.v7i2.29.13318

Levy, S. M., & Civitello, A. M. (2014). Construction operations manual: Policies and procedures (5th ed.). McGraw-Hill.

Permadi, S. C., & Wiguna, I. P. A. (2025). Analysis of factors affecting delays in construction projects in the upstream oil and gas industry of South Sumatra. Eduvest – Journal of Universal Studies, 5(12). https://doi.org/10.59188/eduvest.v5i12.51978

PMI. (2021). A guide to the project management body of knowledge (PMBOK® guide) (7th ed.). Project Management Institute.

Prapti, M. S. (2007). Manajemen risiko proyek: Suatu kajian teoritis. J@TI Undip, 2(2).

Raharjo, M. (2017). Studi kasus dalam penelitian kualitatif: Konsep dan prosedurnya.

Saha, S. K., Patil, A., Dwivedi, A., Pamucar, D., & Pillai, A. S. (2023). Analyzing the interactions among delay factors in construction projects: A multi-criteria decision analysis. Reports in Mechanical Engineering, 4(1), 241–255. https://doi.org/10.31181/rme040116112023s

Sarwani, Baihaqi, I., & Utomo, C. (2024). Causes of delay in EPC projects: The case of Indonesia. International Journal on Advanced Science, Engineering and Information Technology, 14(2). https://doi.org/10.18517/ijaseit.14.2.19744

Shah, R. K. (2016). An exploration of causes for delay and cost overrun in construction projects: A case study of Australia, Malaysia & Ghana. Journal of Advanced College of Engineering and Management, 2.

Simanjuntak, J. T., & Mahendrawan, A. (2015). Factors affecting delay of upstream oil and gas development projects in Indonesia: Case study 2012–2013. In SPE/IATMI Asia Pacific Oil & Gas Conference and Exhibition. https://doi.org/10.2118/176067-MS

Singgih, M. Z. A. (2018). Mengenal project management body of knowledge (PMBOK) fifth edition. https://www.codepolitan.com/mengenal-project-management-body-of-knowledge-pmbok-fifth-edition

Sugiyono. (2017). Metode penelitian kualitatif, kuantitatif dan R&D. Alfabeta.

Viles, E., Carolina, N., & Santilli, A. (2020). Causes of delay in construction projects: A quantitative analysis. Engineering, Construction and Architectural Management, 27(4), 917–935. https://doi.org/10.1108/ECAM-01-2019-0024

Wright, S. (Ed.). (1994). Anthropology of organizations (1st ed.). Routledge. https://doi.org/10.4324/9780203413272

Zagia, F., Kajewski, S., Omrani, S., & Motamedisedeh, O. (2025). Prioritizing the key causes of construction project delay in different countries: A cross-sectional analysis of different project types. International Journal of Construction Management. https://doi.org/10.1080/15623599.2025.2568103

Zept. (2025). Procurement delays & their impact on site progress: A financial risk.

Downloads

Published

2026-02-11

How to Cite

Rifky Basalim, Tri Waluyo, & Suryono Efendi. (2026). A Literature Review from Project Management Point of View on Construction Phase Delays: Study on Oil and Gas EPC Projects in Indonesia. Global Management: International Journal of Management Science and Entrepreneurship, 3(1), 22–28. https://doi.org/10.70062/globalmanagement.v3i1.508

Similar Articles

<< < 1 2 3 4 5 6 7 8 9 > >> 

You may also start an advanced similarity search for this article.